MILESSTONES

 

01.07.2008 Receiving permit from Municipal and construction starts.

27.11.2008 Approval of Switchgear Plant Project

19.02.2009 Gas turbine first ignition

21.04.2009 Temporary Admission (1st stage)

22.04.2009 Gas Turbine System started production to National System(47MW)

08.07.2009 Approval of second stage projects

25.07.2009 Start day of Boiler tests.

06.09.2009 Commissioning of the ACC and vacuum units

06.09.2009 Steam turbine first test starts.

12.09.2009 Steam Turbine production tests began..

17.09.2009 Approval of second stage

23.09.2009 Combined Cycle Power Plant starts to production with all units.